Area 3 - 2018 Water Main Replacement

UPDATE 5/10/2018
On May 1st 2018, excavation for new water main has begun and is going quite well. The water main installation portion of the project should be completed around 5/18/2018 (not including testing, disinfection, tie ins to existing, and new water service lines). Residents have been understanding and patient as we work hard to update our City's infrastructure. Thank you!


UPDATE 4/26/2018


On May 1st 2018, excavation is slated to begin for the new water main to be installed on Morton (from S. Batavia Ave. west to S. Jefferson). Also, new water main will be installed in the alley off Morton St. (from Morton north to Blaine, jog through Blaine, and continue north before terminating).

Many of the homes within the replacement scope MAY have lead service lines into the home. On April 16th 2018, the letter below was sent to all residents that may or may not have lead service lines into the residence.
To learn more about lead service lines, potential health affects, and what you can do to mitigate your risk, please take a moment to read the related articles. 
Water_Main_Replacement
If you would like further information on lead service lines or this project in general, please feel free to contact the City of Batavia Water and Sewer Department at (630) 454-2450. We will be more than happy to discuss.

We will try our best to have weekly updates of progress and changes on this page.