Area 3

Current Status (October 10, 2019)

The watermain passed chlorination this week. Performance anticipates starting residential service connections to the main line the week of 10/14. Notice from the Water Division will be distributed prior to connection.  Next week Performance will complete installation of  storm sewer and sump pump connections on Blaine Street.   Pipes and stone will continue to be delivered onsite and left in the street or parkway for staging, but as we start to wind down for a winter shutdown the additional material will be stored off-site during the winter.  Construction will require local road closures throughout the duration of the project, but the contractor will always provide you access to your home. Please drive with caution through the construction zone.  Work is anticipated to be completed by early November 2019 for a winter shutdown and the remaining work will be completed in the spring of 2020.

Status (October 3, 2019)

Performance Construction completed the water installations for this year and started connecting storm sewer at intersection during the week of 9/30.  Next week Performance will continue installing storm sewer and sump pump connections on Blaine Street.  In addition water service installation could start as soon as 10/10.  Notice from the Water Division will be distributed prior to connection.  Pipes and stone will continue to be delivered onsite and left in the street or parkway for staging, but as we start to wind down for a winter shutdown the additional material will be stored off-site during the winter.  Construction will require local road closures throughout the duration of the project, but the contractor will always provide you access to your home. Please drive with caution through the construction zone.  Work is anticipated to be completed by late fall 2019 for a winter shutdown and the remaining work will be completed in the spring of 2020.

Status (September 12, 2019)

Performance Construction has been working on the Area 3 Storm Sewer Separation & Watermain Replacement project since the week of 7/29. The week of 9/16 Performance should start installing watermain on S Jefferson towards Blaine and then west down Blaine. Pipes and stone will continue to be delivered onsite and left in the street or parkway for staging.  Construction will require local road closures throughout the duration of the project, but the contractor will always provide you access to your home. The road closures will be moving closures corresponding with the construction.  Please drive with caution through the construction zone. Work is anticipated to be completed by late fall 2019 for a winter shutdown and then remaining work to be completed in the spring of 2020. 

Status (September 6, 2019)

Performance Construction has been working on the Area 3 Storm Sewer Separation & Watermain Replacement project since the week of 7/29. The week of 9/9 Performance will finish installing storm sewer on the far west end of Blaine and start installing watermain on S Jefferson towards Blaine and then west down Blaine. Pipes and stone will continued to be delivered onsite and left in the street for staging.  Construction will require local road closures throughout the duration of the project, but the contractor will always provide you access to your home. The road closures will be moving closures corresponding with the construction.  Please drive with caution through the construction zone.  

Status (August 29, 2019)

Performance Construction has been working on the Area 3 Storm Sewer Separation & Watermain Replacement project since the week of 7/29. The week of 8/26 Performance will continue installing storm sewer on Blaine with work also occurring at the intersection of Harrison & Blaine for sanitary improvements . Pipe will continued to be delivered onsite and left in the street for staging. Storm sewer will has been installed on Jefferson between Morton and Blaine and now installation is occurring on Blaine Street heading west past Harrison. Construction will require local road closures throughout the duration of the project. The road closures will be moving closures corresponding with the construction.  Please drive with caution through the construction zone.  Work is anticipated to be completed by late fall 2019 for a winter shutdown and then remaining work to be completed in the spring of 2020.

Status (August 9, 2019)

Performance Construction started work on Wednesday, August 7th.  Storm sewer is being installed first on Jefferson between Morton and Blaine and then will continue on Blaine Street until west of Harrison.  Staging of equipment and materials will take place on the streets affected by construction.  Construction will require local road closures throughout the duration of the project.  The map indicates which roads will see closures over the course of construction. The road closures will be moving closures corresponding with the construction.  At this time work is anticipated to be wrap up for a winter shut down by the end of October 2019 and then start back up in Spring 2020.

Status (July 26, 2019)

Performance Construction has been awarded the Area 3 Storm Sewer Separation & Watermain Replacement project. The contractor anticipates starting in Area 3 July 31st.  Construction will require local road closures throughout the duration of the project. The map indicates which roads will see closures over the course of construction. The road closures will be moving closures corresponding with the construction.  The project will start on Jefferson Street and move north and west. Work is anticipated to be completed by late fall 2019. 

 Map of Affected Streets

Status ( February 1, 2019)

City Staff is finalizing Plans and Specifications for Phase 2. It is anticipated this project will be let for bidding by the end of February and spring/summer construction. A Neighborhood meeting will be held for upcoming construction on Tuesday, March 12th at City Hall prior to the 7 pm Committee of the Whole meeting. Mahoney Creek Stabilization and Maintenance discussions will be from 5:30 to 6PM, Ward 1-Phase 2 Construction meeting will be held from 6 to 6:30 PM and Area 3 – Phase 2 Construction meeting will be held from 6:30 to 7 PM. Additional information will be forthcoming and postcards will be sent to those directly affected by the upcoming construction.

Project Purpose 

The purpose of this project is to start analyzing the combined sanitary and storm sewer system and start separating the storm sewer out. The area numbers are a reference to the Trotter Study that was completed in 2008 for separating the combines system. These improvements will aim to provide adequate pipe capacity per today's design standards that will reduce and eliminate water back up while increasing the ability of the water to flow through the storm system. The City hired Rempe-Sharpe to complete a Phase I preliminary engineering study of the area and propose a list of improvements to alleviate the ponding and drainage concerns for Area 3.

Project Background

During the June 2015 rain event the area bound by Union Street to the north, the old railroad tracks to the west, Garfield to the south and Route 31 for area 3 experienced storm water back-up that resulted in water filling numerous streets, yards, and occasional houses. Since this area is combined with both storm and sanitary sewage the back-ups came up through floor drains and were deemed sanitary back-ups. The City would like to alleviate these back-ups and design a storm sewer system able to handle at least the 10-year event as a standalone system, which is current design practices for new development. As the storm sewer is separated from the combined system, the combined sewer will eventually become just a sanitary sewer.

Construction Impacts

Final engineering has been completed for Area 3 storm outfall and Phase 1. The Outfall was constructed in Fall 2017 and Phase 1 was constructed during the summer of 2018. The remaining Phases, 2 and 3, will be posted below after they have been let for construction. In addition, you can find the notices mailed to the impacted residents for each year's construction.

Project Location

Please see the City's Capital Improvement Map for limits Area 3 Drainage Study.

Project Funding 

This project is funded through the City Council's budget allocated to alleviating drainage issues throughout the city. CIP Sheet (PDF)

Contact Information

If you have any questions about the project please email Andrea Podraza or call 630-454-2757.

  1. Andrea Podraza, P.E., CFM

    Assistant City Engineer

  2. Engineering

    Physical Address
    200 N Raddant Road
    Batavia, IL 60510

    Phone: 630-454-2750
    Fax: 630-454-2351